Factory Registration in Taiwan: Who Needs It, When, and What to Prepare

In Taiwan, a finished factory must still be registered before production can start. Under Article 10 of the Factory Management and Counseling Act, a factory must apply for registration once construction is complete, and may begin manufacturing or processing goods only after the competent authority approves the registration [1].

Registration is the last step in building a factory, but many of its conditions are fixed much earlier, during site selection and design. This article explains who needs to register, when to apply, which documents to prepare, and what to keep in mind during design.

Who needs factory registration

Under Article 3 of the Act, a factory is a fixed place for manufacturing or processing goods where the factory floor area reaches a set threshold, or the production equipment reaches a set power capacity or thermal energy [1]. The determination standards set by the Ministry of Economic Affairs are as follows [2]:

Businesses below these thresholds that manufacture or process goods at a fixed place may still apply for registration (Article 3, paragraph 3) [1]. For logistics operators, pure chilled or frozen storage does not count as a factory; but if food is also manufactured or processed on the same premises, factory registration may be required.

First check: do you need a factory establishment permit?

Where the law requires a factory’s establishment to be approved by the industrial competent authority, or the central competent authority has announced that approval is required, an establishment permit must be obtained before the factory is set up (Article 11). Once the permit is granted, registration must be completed within the approved period, which may not exceed two years; with good reason, extensions of up to one year each may be applied for, no more than three times (Article 12) [1].

If your industry falls into this category, the establishment permit should come first in the project programme.

When registration is refused

Under Article 15, a factory may not be registered, or have its registration amended, in any of the following cases [1]:

The second and third items bear directly on site selection and design: the land must comply with land-use controls, the building must be lawful, and the use stated on the occupancy permit must match the factory use.

What to prepare for the application

Factory registration is handled by the municipal or county (city) government (Article 2) [1], and requirements vary slightly from place to place. The documents listed by the Department of Economic Development, Taipei City Government, are a typical example [3]:

The same guidance states that the registration fee is NT$5,000 per application, payable after approval; building area is taken as recorded on the occupancy permit; factories making products subject to plant establishment standards are approved only after a site inspection confirms compliance; and general food factories require a site inspection or a pass certificate from the health authority [3]. Some cities and counties offer online applications, such as Kaohsiung City’s online factory registration system [4].

After registration: changes and penalties

What to get right at the design stage

Frequently asked questions

Does a cold store need factory registration?
Not if it only chills, freezes, repackages or packages goods: under the Ministry of Economic Affairs’ determination standards, that falls outside the definition of a factory. If food is also manufactured or processed there, registration may be required. The competent authority’s determination is what counts.
Can we start production and register later?
No. Under Article 10 of the Factory Management and Counseling Act, manufacturing or processing may begin only after registration is approved. A factory that produces without registration will be ordered to stop work and fined under Article 30.
Who applies for factory registration?
The owner (the person responsible for the factory), or an agent they appoint, applies to the municipal or county (city) government. The layout plan and area calculations must be based on the building survey plan or the as-built drawings, and on the occupancy permit.

Planning a new factory?

Tell us what you make, where you are thinking of building, and your expected power and water use. We will reply with what needs to be confirmed first at the site selection and design stages.

Write to info@wzwx-group.com or use our contact form.

Send enquiry info@wzwx-group.com

Sources

  1. Factory Management and Counseling Act, Articles 2, 3, 10 to 16 and 30, Laws & Regulations Database of the Republic of China (Taiwan), in Chinese: https://law.moj.gov.tw/LawClass/LawAll.aspx?pcode=J0030043
  2. Standards for determining the scope of manufacturing and processing, and the area, power capacity and thermal energy thresholds, of factories (工廠從事物品製造加工範圍及面積電力容量熱能規模認定標準), Articles 2 and 3, Laws & Regulations Database of the Republic of China (Taiwan), in Chinese: https://law.moj.gov.tw/LawClass/LawAll.aspx?pcode=J0030117
  3. Department of Economic Development, Taipei City Government, Documents required for factory registration, in Chinese: https://doed.gov.taipei/cp.aspx?n=8CA2C2EFFB9B7DA3
  4. Kaohsiung City Government, online factory registration system, in Chinese: https://factory.kcg.gov.tw/FSA/web_page/index.jsp

This article is general information based on public sources available in November 2026 (the laws and official sources cited were each checked on 13 November 2026). It is not legal, tax or investment advice.