“How much will it cost to build a factory?” is the question clients ask most, and the hardest to answer with a single number. For the same floor area, a single-storey warehouse and a multi-storey food factory with cold stores or cleanrooms can differ widely in cost.
This article explains what makes up the total cost of a factory, the main factors that drive construction cost, the published data you can refer to, and how to control the budget during design. It does not quote a cost per ping (the Taiwanese unit of floor area, about 3.3 m²): a unit rate given before the site, the process and the specification are understood does little to support a decision.
Is there published cost data you can refer to?
Yes, but you need to understand what it is for and where its limits lie:
- Bulletin No. 4 construction cost standard tables, National Federation of Real Estate Appraisers Associations, Republic of China: A new edition was issued on 6 December 2024. It sets out unit-rate ranges by city or county, form of construction and number of storeys for uses including housing, offices, factories and warehouses, and is the main reference in valuation practice. The Federation states that the new edition raises rates by between 8% and 20%. It also cautions that the bulletin’s unit rates are based on registered title area, which differs from the floor-area basis commonly used in the industry, so particular care is needed when quoting them [3].
- Construction Cost Index, Directorate-General of Budget, Accounting and Statistics (DGBAS), Executive Yuan: Useful for comparing construction costs at different points in time [5]. The Federation notes that from the previous revision of the bulletin to the end of 2024, the building works component of the construction cost index rose by about 8% to 13% [3].
These data are references for valuation and trends, not contractor quotations. Items such as refrigeration, cleanrooms, process equipment and special foundations still need to be estimated for your project by a professional quantity surveyor.
Working out a budget for a new factory?
Tell us what you make, how much space you need and where you are looking. We will reply with the factors that will most affect your budget, and which assessments are worth doing first.
Write to info@wzwx-group.com or use our contact form.
Sources
- Industrial Innovation Statute, Article 48 (development and management fund), Laws & Regulations Database of the Republic of China (Taiwan), in Chinese: https://law.moj.gov.tw/LawClass/LawAll.aspx?pcode=J0040051
- Building Act, Article 29 (permit fees), Laws & Regulations Database of the Republic of China (Taiwan), in Chinese: https://law.moj.gov.tw/LawClass/LawAll.aspx?pcode=D0070109
- National Federation of Real Estate Appraisers Associations, Republic of China, notice of the new edition of Bulletin No. 4 issued on 6 December 2024, and press release (11 December 2024), in Chinese: https://www.rocreaa.org.tw/news_detail.php?NsId=QD48PyomJTQ1OEAoKyMlXis%3D
- Taiwan Power Company, Operating Regulations, Chapter 7, Line Installation Charges (from Article 71), in Chinese: https://www.taipower.com.tw/2289/2484/51434/51760/
- Directorate-General of Budget, Accounting and Statistics, Executive Yuan, Construction Cost Index: https://www.stat.gov.tw/Statistics.aspx?CaN=460&n=3906
This article is general information based on public sources available in November 2026 (the laws and official sources cited were each checked on 13 November 2026). It is not legal, tax or investment advice.