Building a Factory in Taiwan: Steps, Permits and Timeline

Building a factory in Taiwan follows five broad steps: choose where to build, check the site, design, obtain permits, then construct and register the factory. The process is well defined, but the order of decisions matters, and choices made in the first weeks shape cost and schedule for years.

This guide is for Taiwanese companies building a new plant and international manufacturers setting up in Taiwan. It explains each step, what you decide along the way, and where projects most often lose time.

Step 1: Choose where to build

The type of land you choose affects price, speed of approvals, incentives and what you are allowed to build. Taiwan offers both general industrial zones and special-purpose parks. Government figures list 135 industrial areas covering about 44,000 hectares as of April 2025, including technology industrial parks, science parks and agricultural technology parks (Legislative Yuan, 2025).

You decide: park or non-park land, buy or lease, and which region best serves your suppliers, customers and workforce.

Step 2: Check the site before you commit

Before buying or signing a lease, confirm that the site can take your factory, now and as you grow. The key checks are zoning and permitted use, floor-area ratio and coverage, setbacks, applicable codes, truck access, power and water capacity, wastewater, flood risk, ground conditions, earthquake and fault-line risk, environmental constraints and height limits.

We cover each of these in What to Check Before Buying Industrial Land. Do this before you buy, not after. Industrial land holds many hidden traps for inexperienced buyers, and there is nothing worse than owning a site that cannot build what you need. A few weeks of checking here can prevent months of delay, or a costly wrong purchase.

You decide: whether to buy or lease, and which site.

Step 3: Design

Design moves from the big picture to the detail, with client approvals at each stage.

  1. Masterplan. Organise production, warehousing, offices, staff areas, truck yards and future expansion across the site.
  2. Concept and schematic design. Set the building’s form, structure, daylight, materials and character.
  3. Detailed design. Coordinate with structural, MEP and process engineers and your equipment suppliers. Equipment loads, clean-room or hygiene zones, and utility routes must be fixed here.
  4. Permit drawings. Prepare the submission set for the building permit.

The biggest causes of redesign at this stage are late information about production equipment, and changes to it: a revised production line, a switch to a different machine brand with different dimensions, or a change in the products to be made. Bringing your process engineers and key suppliers in early saves time.

You decide: layout, design direction, budget and final specifications.

Step 4: Permits and approvals

A factory in Taiwan typically passes through three main approvals: a building permit before construction, a use permit after completion, and factory registration before production. Depending on the industry, a factory establishment permit may be needed before construction too.

  1. Factory establishment permit (工廠設立許可), if your industry requires one before building.
  2. Park design or landscape review, where the park requires it.
  3. Environmental assessment, if the project’s scale or location triggers one. Many parks have already completed this at park level.
  4. Building permit (建造執照). Drawings are reviewed for zoning, building code, structure and fire safety, and must be signed by a licensed Taiwan architect.
  5. Use permit (使用執照). Issued after completion and inspection, confirming the building matches the approved drawings.
  6. Factory registration (工廠登記). Registers the factory, its premises and its production with the authorities so it can operate.

Where time is lost: incomplete submissions, repeated changes to the design criteria during the design stage, slow decision-making, design changes after the building permit is issued, and differences between what is built and what was approved, which delay the use permit.

Step 5: Construction and supervision

Once the building permit is issued and a contractor appointed, construction begins. The architect’s role now is to make sure what is built matches the design and the approved drawings.

Full site supervision means regular inspections, reviewing contractor drawings and material samples, resolving problems on site, and coordinating with equipment installers. It protects quality, and it protects the use permit: changes made on site without approval are one of the most common reasons for delays at completion.

Interiors for offices, canteens, showrooms and staff areas can be designed and built alongside the main construction.

How long does it take?

There is no single answer, and anyone who gives one before understanding your project is guessing. These factors make the biggest difference:

Once we understand these, we can give you a realistic schedule. See How We Work for how we approach this.

Case study: T-HAM PABP Meat Processing Factory, Pingtung

T-HAM, Taiwan’s oldest and largest meat-processing brand with over 50 years of history, built its new factory in the Pingtung Agricultural & Biotech Park. The LEED Gold complex includes a 22,000 m² main factory, a 650 m² diner and gift shop, and a wastewater treatment building. It produces 45 tonnes of processed meat products a day and 12,000 tonnes a year. The project began in 2015, and the factory has been in use since 2018.

The brief. T-HAM set four goals for the project:

The challenges.

The approach. A typical meat-processing plant is a sealed, refrigerated box. Instead, we placed the offices, laboratories, canteens and changing rooms at the front, behind a glazed façade, with refrigerated production (−35 to 13°C) at the rear. Workers who spend their shifts under artificial light now have daylight and views on their breaks. Locally made materials, efficient MEP design saving about 20% of electricity, and water-efficient fixtures with rainwater reuse cutting water use by about a third earned LEED Gold.

The results. According to T-HAM’s factory manager, the plant meets the Japanese and Singaporean export requirements and has greatly improved production efficiency. The retention rate of existing workers has doubled, and hiring new workers has become much easier.

View the project

Frequently asked questions

Who signs the drawings?
Building permit drawings must be signed by a licensed Taiwan architect. Ours are signed by a licensed architect partner who has worked as part of our project team for many years.
Should we build in an industrial park?
Parks offer ready infrastructure and simpler environmental approvals, but may restrict industries, lease rather than sell land, and add design reviews. Non-park land offers more choice but needs more checking.
When should we involve an architect?
Before choosing land. Many of the decisions that set cost and schedule are made at site selection.
Can you manage the whole process?
Yes. One point of contact: we handle everything from land due diligence through masterplan, architecture, interiors, furniture and construction supervision.

Planning a factory in Taiwan?

Tell us what you make, where you are looking and how many people will work there. We’ll reply with the likely route, the questions to answer first, and how we can help.

Write to info@wzwx-group.com or use our contact form.

Send enquiry info@wzwx-group.com

Sources